Project Information

  • Description

    The Department proposes to replace the S-91 (River Road) bridge over Burden Creek in Charleston County. The existing S-91 facility is comprised of two, 10-foot travel lanes with approximately one-foot paved shoulders.

  • Proposed Improvements

    The project includes replacing the existing bridge structure and constructing the roadway to meet current design and safety standards. The proposed roadway section will now provide two, 12-foot travel lanes with two-foot paved and eight-foot grassed shoulders.

  • Purpose and Need

    The purpose of the project is to correct structural deficiencies of the existing S-91 bridge over Burden Creek.

Estimated Schedule

  • Timeline item 1 - incomplete

    Drop-in Public Meeting

    Anticipated Late 2025

  • Timeline item 2 - incomplete

    Right of Way Acquisition

    February 2026

  • Timeline item 3 - incomplete

    Construction

    February 2027

    Construction Duration - Approximately 6 months