Project Information

  • Proposed Improvements

    The project will relocate the current alignment slightly to the west to accommodate a 25-mph design speed and has a profile slightly above existing. The project utilizes traditional bridge elements and minimizes impacts while replacing the bridge and upgrading the roadway to current standards.

  • Purpose and Need

    The purpose of the proposed project is to eliminate structural deficiencies and to provide a bridge and roadway approaches that meet current SCDOT standards.

Estimated Schedule

  • Timeline item 1 - incomplete

    Right of Way Acquisition

    Spring/Summer 2025

  • Timeline item 2 - incomplete

    Construction

    Spring 2027

    Construction Duration - Approximately 18 months